IESImpactEnvironmental Services+64 21 263 6697
The roof steel frame bolted together at ground level inside the first ring of a tank shell, on the concrete pad beside the site buildings
Fire water

Fire water tanks

Two tanks on one pad, holding the fire suppression supply for a fuel precinct.

Two fire water storage tanks built side by side at a fuel precinct. Together they hold the supply for fire suppression to the administrative buildings on site.

Sector
Fire water
Location
North Island
Tanks
Two
Capacity
540,000 litres each
On site
6 weeks
Build & Install in full

North Island. Marker position is indicative.

Reinforcing steel laid for a tank foundation at sunset, crew working

Begin with a call

Tell us what the tank is doing and roughly where it is. Every job is quoted on its own, so the first step is a phone call.